Construction underway on BISD bond projects
Jun 05, 2009 | 852 views | 0 0 comments | 10 10 recommendations | email to a friend | print
A.C. Jones High School will receive $3,555,148 of the $12 million bond issue to spend on campus improvements. The projects are scheduled to be completed by August 2010. Superintendent Dr. John Hardwick Jr., left, poses with Leticia Muñoz and BeBe Adamez, two members of BISD’s master planning task force. High School Principal Joe Reyes, at right, stands next to school board trustee Viola Salazar.
view slideshow (5 images)
Beeville ISD voters approved a $12 million bond sale last year to finance campus improvements districtwide.

Starting this week, they’ll get to see how their tax dollars are being spent.

Contractors are scheduled to fan out across the district and begin construction projects at local campuses.

Work on the campuses has been underway for quite some time but those projects have not been very visible. This month contractors will begin working on projects that are more visible, such as remodeling entryways at some of the campuses and replacing rooftop air conditioning units.

“The district continues to value the importance of effective communication with our taxpayers as they trust us to be good stewards of the dollars spent on the facilities projects that were approved in a bond election,” BISD Superintendent Dr. John Hardwick said. “Some of the more visible projects at our three elementary schools and Moreno Middle School will be accelerated over the summer months. Our school board receives a monthly progress report on the status of projects and how we are doing with the available funds. To date all projects are on schedule and at or under budget.”

The projects at each campus are scheduled to be completed by August 2010.

Here’s how the bond money is being spent at each campus, and how far along the projects are at each campus:



R.A. Hall

Elementary School

Amount of bonds allocated to campus — $1,752,613

Projects scheduled

• Replace rooftop A/C units ­— 15 percent completed.

• Upgrade restrooms — 50 percent completed.

• Install new intercom system — 100 percent completed.

• Electrical upgrades — 100 percent completed.

• Library expansion — 100 percent completed.

• Replace roof — 100 percent completed.



Moreno Middle School

Amount of bonds allocated to campus — $2,010,000

Projects scheduled

• Repair roof leaks — 100 percent completed.

FMC Elementary School

Amount of bonds allocated to campus — $1,672,103

Projects scheduled

• Replace rooftop A/C units — 10 percent completed.

• Replace roof — 20 percent completed.

• Restroom upgrades — 50 percent completed.

• Install new intercom system — 100 percent completed.

• Electrical upgrades — 100 percent completed.



Thomas Jefferson Elementary School

Amount of bonds allocated to campus — $875,026

Projects scheduled

• Replace rooftop units — 10 percent completed.

• Install new intercom system — 100 percent completed.

• Second floor hardware — 100 percent completed.

• Electrical upgrades — 100 percent completed.

• Paint gym — 100 percent completed.

• Replace rooftop A/C units — 0 percent completed.



A.C. Jones High School

Amount of bonds allocated to campus — $3,555,148

Projects scheduled

• Refurbish homemaking department — 25 percent completed.

• Install surveillance cameras — 100 percent completed.

• Install new auditorium lighting and sound system — 100 percent completed.

• Rehabilitate track — 100 percent completed.

• Improve site drainage — 100 percent completed.

• Build new transportation facility — 0 percent completed.

• Pour new concrete foundation/slab — 100 percent completed.